How does a project move from phase to phase, and how do I close it?

The phase line, above the tabs of each project, shows where it stands, from Assignment to Closed. It moves on automatically from what you record. You correct it from each phase's menu, stop it with «On hold» or «Cancel the project», and the project closes through the closing check.

On this page How does the phase move on? When does Handover come? How do I correct the phase? Which phases does a project have? What do «On hold» and «Cancel the project» do? How do I close a project? What is checked before the project closes? What are «How did it go?» and the Summary? How does a closed project open again? What about work items? Where else is the phase shown? Who changes the phase, closes and reopens?

At the top of every project's page, above the tabs, the line of phases shows where it stands: Assignment → Site inspection → Study → Submission → Approval → Handover → Closed. Assignment, Study, Handover and Closed are always there. Site inspection, and Submission together with Approval, are there when the project needs them. The phases it went through carry a ✓ and the current one shows how many days it has lasted. Its menu says since when, and whether it came Automatic or Set by hand, and by whom.

How does the phase move on?

Automatically, from what you already record:

PhaseComes when…
Site inspectiona field work appointment of the project is completed
Studya work item is started
Submissiona wait on an authority opens for the project
Approvalthe authority answers. If a new wait on an authority opens, the project goes back to Submission
Handoveryou approve it
Closedthe project passes the closing check

The line only goes to phases the project has. A project on hold does not move on automatically.

If the item action that moved the phase is undone (the item is reopened, or its wait on the authority is lifted), the phase goes back to where it was, unless you changed it yourself in the meantime. When somebody else’s action on an item moves the phase, the project’s lead and co-lead are notified, and the History says who did it and with which item.

When does Handover come?

Not automatically. When every item is done or cancelled, the project page says «Every item is done.» and asks Ready for handover?, and the same suggestion appears under Ready in the Control Centre. Hand over moves the project to the «Handover» phase, while Not yet hides the question until the next time you open the page. A project in Handover has been delivered. It no longer counts as open, and only the closing check is left.

How do I correct the phase?

Click a phase on the line. Its menu offers, depending on where it stands, Move here, Back to «…» or «…» is done. Your correction holds until the next automatic record. After a correction, Automatic under the project page's ⋯ undoes it and the line follows the records again.

Which phases does a project have?

A new project takes its phases from its template, while a project without a template has both Site inspection and Submission with Approval. On the project's page you change them under ⋯, in the Phases section: Needs a site inspection and Submitted to an authority. A phase that will not happen on this project is taken out with Skip the phase in its menu. It leaves the line, stays in the History and comes back under ⋯ › Restore a skipped phase. Assignment, Handover and Closed cannot be skipped.

What do «On hold» and «Cancel the project» do?

They are set by hand only, from a phase's menu (On hold here…, Cancel the project here…). The line stops at the phase the project is in, and the later phases freeze.

  • On hold: the window asks, optionally, Who are we waiting for? and for a note. If you choose one, a wait opens as always. While it waits, the project does not move on automatically and counts neither in health nor as open, while time is recorded as usual. Continue, in the stop's menu on the line, starts it again where it stopped.
  • Cancel the project: the window shows what is still open (items, appointments) and asks, optionally, for a reason. A cancelled project leaves the open ones. Reopen, in the same menu, brings it back to the phase where it stopped. If the project had a published presentation in ErgoWeb, cancelling takes it down and keeps it as a draft. «Reopen» does not publish it again, and you publish it yourself.

How do I close a project?

When the project is in Handover, press the Closed arrow on the phase line, or Close the project… in Handover's menu. Before Handover the Closed arrow cannot be pressed. The window has three steps: Check, How did it go? and Summary. The only way to Closed is through here.

What is checked before the project closes?

Stops the closingOnly warns
Your own items that are neither finished nor cancelled. You finish or cancel them from there, with a reasonOpen tasks, unticked checklist points, a wait that is still running
Required checklist points, when the office has required points switched on. For these you can declare «not applicable», with a reasonPartner items still open (the partner changes their status), items with no effort estimate, no time recorded on the project, items with an unpaid balance

The button tells you how many warnings you are closing with. Only someone who can see amounts sees the unpaid balance warning, and even then without the amount.

A project's checklist shows the steps done and the ones to come, each with the person in charge and a date.
A project › Checklist

What are «How did it go?» and the Summary?

«How did it go?» is optional: As planned, With small or With significant deviations, the reasons and a short note. The Summary shows what is frozen at closing, and it does not change afterwards. From the project's Closing summary card you download it as a PDF or save it to the project's files.

How does a closed project open again?

Through Reopen on the closing summary, or from the menu of the Closed phase on the project's line (it opens the same form): you write why and choose where it returns, to Handover (the default) or to the last work phase before it. The closing and the reopening both stay in the project's history.

What about work items?

Work items keep their own statuses: Open, In progress, On hold, Completed, Cancelled. When an item is put On hold, its card, like the status change in «My tasks», asks whom it waits for (Customer, Public service, Partner, someone in the office, Other), since when and, optionally, what is awaited; the person in charge of it can answer too. That becomes the project's wait, and a late item that waits shows in the Control Centre as waiting, not as overdue. They have no phase, but their progress moves the project's phase. An item's payment is a separate label (Unpaid, Partially paid, Paid in full), so a project in Handover can still have unpaid items.

Where else is the phase shown?

  • Project list: the Phase column, with a small line and the phase's name. Under it is since when, or, on hold, who we are waiting for and for how many days, or, for a cancelled project, the day it was cancelled.
  • Phone: on a project's page the same line, read only (the current phase by its name, the others by their icon). In My projects you see each project's phase as in the Project list.
  • Home: the Projects by phase card, with the open projects of each work phase and, apart, the ones on hold.
  • Statistics: the period's projects by phase. On the Project flow tab there is How long each phase takes for the projects closed in the last 12 months.
  • In the Control Centre: the handover and closing suggestions, under «Ready». Health judges only projects that are not on hold.
  • ErgoWeb: a new project presentation in ErgoWeb opens only for a project in Handover or Closed, while the ones that already exist stay.
  • ErgoAI and AI agents: they tell which phase a project is in and, when Projects is on «Entry and deletion», change the phase, put it on hold or cancel it, always with a preview and your approval. Closing happens in Ergothiki only.

Who changes the phase, closes and reopens?

Anyone who may create and change projects in your office:

PermissionOffice ownerOffice administratorProject managerTechnical staffSecretariatAccountingWebsite manager
Create and edit projects and work itemsyesyesyesnoyesnono